RFP Number: RFP26-069
Project Name: Hydropower Forecasting Pilot and Delft-FEWS Platform
Domain Name: Infrastructure
Application Closing Date: 5 pm (Phnom Penh Time), 4 January 2027
Assignment Duration: 18 months from contract commencement
Location of assignment: Phnom Penh
1. Background
1.1. About CAPRED
The CAPRED Facility is Australia's flagship bilateral economic development program in Cambodia, focusing on economic recovery and resilience over the next five years, with a possible three-year extension. The Facility supports Cambodia in implementing a range of important economic reforms to support the country's economic transition. These interventions and reforms aim to encourage more productive and inclusive public and private investment, promoting a resilient, inclusive, and sustainable economy (RISE).
1.2. About CAPRED’s energy portfolio
CAPRED supports Cambodia’s transition towards a cleaner, more reliable and affordable energy system. CAPRED works with the Ministry of Mines and Energy (MME), Électricité du Cambodge (EDC), the Electricity Authority of Cambodia (EAC) and private-sector stakeholders to strengthen energy-sector planning, accelerate renewable-energy integration, promote energy-efficiency investment and build institutional and technical capacity.
1.3. Hydro forecast system assessment findings
Hydropower remains a critical component of Cambodia's power system and accounts for approximately 50% of the country's electricity generation mix. Accurate forecasting of hydropower availability supports more informed operational decision-making, including generation planning, system balancing, reserve management and power procurement.
Recognising the importance of improving hydropower forecasting capability, CAPRED, in collaboration with EDC and with the endorsement of MME, commissioned an assessment to identify a suitable hydropower forecasting approach for Cambodia. The assessment reviewed current forecasting practices, available meteorological, hydrological and operational data, international experience, institutional arrangements, and potential forecasting-system options.
The assessment found that hydropower plays a critical role in Cambodia's power system, but EDC's ability to forecast hydropower output remains constrained by several challenges. Existing forecasting practices rely heavily on manual processes, spreadsheet-based analysis, operator judgement and publicly available weather information. Forecasting becomes particularly challenging during the transition between the wet and dry seasons, when changes in rainfall patterns can significantly affect reservoir inflows and hydropower generation. Under these conditions, uncertainty in hydropower output can affect generation planning, system balancing and power procurement decisions.
The assessment also identified several structural constraints, including fragmented data sources, limited access to hydrological observations from hydropower operators, inconsistent data-sharing arrangements, limited integration of meteorological and operational data, and the absence of an integrated forecasting workflow. As a result, forecasting capability is generally limited beyond very short-term operational planning.
Four potential options were assessed:
1. An external forecasting service;
2. An externally hosted Delft-FEWS platform, with the gradual transfer of knowledge and responsibilities to EDC;
3. A Delft-FEWS platform hosted and operated by EDC from the outset; and
4. A fully customised forecasting system.
The assessment concluded that a phased implementation pathway combining Option 1 (External Forecasting Service) and Option 2 (Externally Hosted Delft-FEWS Platform) offers the most suitable near-term approach for Cambodia. The two options can be implemented as independent but complementary components. Option 1 involves testing external forecasting services using historical and forward inflow forecasts to evaluate their performance under Cambodian operating conditions. Option 2 involves deploying an externally hosted Delft-FEWS platform to provide an integrated framework for data management, forecast generation, visualisation and reporting, while supporting the development of EDC’s forecasting capabilities.
Based on these findings, EDC and CAPRED agreed to proceed with a hydropower forecasting pilot involving multiple Hydropower Forecasting Service Providers (HFSPs). The pilot is expected to focus on 5-7 hydropower reservoirs with different catchment and operational characteristics, subject to EDC confirmation of the final locations. The Cardamom hydropower cascades are currently considered the most likely pilot area due to their challenging hydrological conditions and suitability for testing short-term inflow forecasting performance under Cambodian operating conditions. However, the final pilot locations will be confirmed by EDC based on operational priorities, data availability and stakeholder participation.
2. Objectives
CAPRED seeks to engage qualified Hydropower Forecasting Service Providers (HFSPs) and consortiums to support the demonstration, testing and evaluation of hydropower forecasting solutions under Cambodian conditions and to support the development of a suitable hydropower forecasting system for EDC.
The pilot aims to:
3. Scope of the assignment
The phases assignment will be implemented over an indicative period of 18 months and comprise two separate components covering five to seven selected hydropower reservoirs in Cambodia: Phase 1 – Hydropower Forecasting Pilot, for the provision and evaluation of hydropower forecasting services; and Phase 2 – Delft-FEWS Platform Deployment, for the configuration and deployment of an externally hosted Delft-FEWS platform. The two are independent, and providers may submit proposals for either phase or both. CAPRED intends to select a minimum of two HFSPs and/or consortiums to participate in Phase 1. The pilot will evaluate and compare alternative forecasting approaches based on forecast performance, operational usefulness and value for money. Participation in Phase 1 does not constitute a prerequisite for participation in Phase 2, and providers may be selected for either phase independently or for both phases.
Data availability
Based on the hydropower forecasting assessment, a range of meteorological, hydrological, reservoir and operational datasets are expected to be available for the pilot, subject to confirmation by EDC and participating hydropower operators. These may include historical reservoir inflow and water level records, reservoir operational data, SCADA-derived operational datasets. CAPRED and EDC will facilitate engagement with relevant data owners and support access to available datasets; however, applicants should clearly identify any additional data requirements and assumptions in their proposals.
| Phase | Key Tasks | Detailed Activities | Key Deliverables | Indicative Timeline |
| Phase 0: Project Preparation | Task 0.1: Project Inception and Data Assessment |
|
Implementation Plan | Month 1 |
| Phase 1: Hydropower Forecasting Pilot | Task 1.1: Historical Forecasting (Back-testing) |
|
Historical Forecast Dataset | Month 2-5 |
| Task 1.2: Forward Forecasting |
|
Forward Forecast Dataset | Month 5-11 | |
| Task 1.3: Capacity Building and User Engagement |
|
Training material | Month 11-12 | |
| Task 1.4: Performance Assessment and Selection of Preferred Solution |
|
NA | Month 12-13 | |
| Phase 2: Delft-FEWS Platform Deployment | Task 2.1: Delft-FEWS Platform Configuration and Integration |
|
Delft-FEWS Requirements and Concept Design Report | Months 13-15 |
| Task 2.2: Operational Testing and Training |
|
Training material and user guide | Months 15-17 | |
| Task 2.3: Handover and Scale-up Roadmap |
|
Final report and handover package | Months 17-18 |
While outputs Phase 1 are expected to enhance implementation of the Phase 2 Delft-FEWS platform, CAPRED and EDC may elect to commence Phase 2 earlier where sufficient information is available, and institutional readiness has been confirmed. The sequencing and timing of activities may therefore be adjusted during implementation.
4. Qualifications, knowledge and experience required
Applications are open to legally registered national or international organisations or consortiums that demonstrate the qualifications, experience and technical capacity relevant to the phase(s) for which they are applying.
Applicants may submit proposals for Phase 1 – Hydropower Forecasting Pilot, Phase 2 – Delft-FEWS Platform Deployment, or both phases. Applicants proposing for both phases must demonstrate the combined capabilities required for both components, either directly or through a consortium.
4.1. Organizational experience &technical qualifications
Phase 1 – Hydropower Forecasting Pilot
HFSPs or consortiums must demonstrate:
Phase 2 – Hydropower Forecasting Pilot
HFSPs or consortiums must demonstrate:
4.2. Key Personnel
The proposed team should collectively demonstrate the expertise and experience required for the phase(s) proposed.
For Phase 1, the proposed team should collectively demonstrate capabilities in:
For Phase 2, the proposed team should collectively demonstrate capabilities in:
Applicants should clearly describe the roles and responsibilities, relevant qualifications and experience, and level of effort of proposed personnel and demonstrate how the team collectively meets the requirements of the phase(s) proposed.
4.3. Other Qualifications
5. Evaluation criteria
CAPRED will use an objective and reliable process to evaluate each proposal. The proposals and responses will be evaluated based on (in no particular order):
1. Compliance with this Request for Proposals (RFP).
2. Demonstrated understanding of the assignment and ability to meet the required deliverables and timeline.
3. Relevant experience of the consulting firm/consortium in similar assignments
4. Expertise of individuals and the overall team nominated to deliver the service. CAPRED reserves the right to reject any individual proposed and to ask the supplier to provide an alternative.
5. Past performance on similar assignments, including reference checks
6. Quality and relevance of previous work examples
7. Proposed financial plan for the services.
Note: While price is a factor, it is more important that the applicant can demonstrate value for money. CAPRED reserves the right to contract more than one supplier for these services and may actively seek to contract more than one supplier to ensure the supply of technical services. CAPRED reserves the right to vary the contract terms and to exercise the option period at its sole discretion.
Due diligence checks will be conducted on the organization/s and individuals nominated in the RFP prior to awarding contract/s.
6. How to Apply
The proposal, including the Technical and Financial Response Forms, must be submitted no later than 5 pm (Phnom Penh Time), 04 January 2027, by email to procurement@capred.org with “RFP – Hydropower Forecasting Pilot and Delft-FEWS Platform” in the subject line. Any proposal submitted after this deadline will not be considered.
The applicant is required to submit the Response Form in English (forms provided separately). The Financial Response Form should provide a clear and itemised cost breakdown for each phase and task of the assignment. The proposed budget should include all costs necessary to deliver the assignment, including professional fees (e.g., daily rates, lump-sum/task-based fees, per-reservoir or per-MW rates, as applicable and reflected in the Financial Response Form), software licensing (if applicable), cloud hosting and storage, third-party data subscriptions, system integration and configuration, training, workshops, travel, technical support, maintenance, and any other associated costs. Applicants should also clearly identify any assumptions, exclusions, dependencies, or conditions relevant to their proposal.
The program will host a Q&A session on 15 December 2026 (14:00–15:00 Cambodia time) via Microsoft Teams. Interested applicants may join the session using the details below:
CAPRED is available to answer questions or provide further clarification on the scope of work. Enquiries should be submitted to procurement@capred.org with the subject line “Hydropower Forecasting Pilot and Delft-FEWS Platform – Enquiry” no later than 16 December 2026.
Attachments:
Cowater International is an equal opportunity employer, basing employment on merit and qualifications as they relate to the professional experience and position expectations. Cowater does not discriminate against any employee or applicants on the basis of race, religion, sex, gender identity, disability, age, or any other basis protected by law. CAPRED aims to have a diverse workforce and a workplace that is supportive of gender equality, disability and social inclusion. Women, people with disabilities and other minorities are highly encouraged to apply.